Originally Posted by zhrike
Normally when we do Bill of material (BOM) we get the average distance per location, In this way you have a safe BOM espcially if you have a deadline to catch.
Example:
You have 100 nodes to do.. Shortest distance from MDF/IDF is 20 meter and longest is 90:
This is the computation:
(20+90) /2= 55 meters
55 * 100 = 5,500 meters
=5,500 /305 = 18 boxes of UTP cable
305 meters is the normal length of UTM cable per box..